Contact

Deptford Foundry

Client:   Anthology

Contractor:   John Sisk & Sons

Architect:   Associated Architects

Location:   Deptford, London

Balconies:   152

Download full case study

Download

Deptford Foundry is located in a historic area of south-east London and sits on of a former metal foundry dating back to 1831 and once home to engineer Josiah Stone. Once a thriving centre of exceptional design, the area is now home to premium apartments, developed by Anthology, each benefitting from access to private balconies and terraces.

The area’s rich industrial heritage is reflected in the design of the balconies featuring tie wires and bronze Cassettes® and soffits.

Challenge

Deptford Foundry is located tightly between to two railway lines, limiting room for site equipment and adding an element of complexity to the install. Due to safety concerns the site team could not go over the boundary over the railway line leaving minimal space for cranes to manoeuvre the balconies into place.

Solution

The proximity of the railway lines meant that traditional balcony designs would have been hazardous to install as nothing could hang over the boundary in the process. Sapphire’s Glide-On™ solution overcame these concerns as the modular prefinished design arrived to site complete and ready for install. The project manager commented that the offsite manufacture of our balconies was “invaluable to this site because of the issues of site logistics”.

The simplicity of the install process meant the balconies could Glide-On™ to the awaiting arms and secured in place without the need for installers working below a live load. Installers remained inside the apartments behind our internal door guards preventing any risk of the leading edge. Once the balconies were on the arms they could be safely bolted in place and the final boards of decking could be fixed in place.

While working alongside the railway lines would often be a headache for traditional balcony methods the Glide-On™ system made light work of the tight space. The project manager said, “balconies were installed straight from the lorries” and that the system was “fantastically simple”.

Our logistics team worked with the site team to ensure the balconies arrived when they were needed and when the site was ready for install. The site team reported a fast install limited only by the façade progress and the needs of other trades on site.

Installation Process

Step 1: Cast in anchors were cast into the slab & incorporated thermal break connections offering superior rigidity to the balconies.

Step 2: Cassette® balconies were preassembled offsite, including the balustrades, decking & soffits.

Step 3: Cassette® balconies were transported with balconies ‘nested’ onto each pallet making transport both cost effective & safe. Balconies were pre-slung offsite ready for installation upon arrival.

Step 4: Once lifted into position, the Cassettes® simply Glide-On™ to the pre-erected support arms, before completing the simple mechanical fixings.

Case Studies